Delivery of concrete piles via Mokapu Road gate
5 Feb 2013

Production pile deliveries will be made via the Mokapu Road gate throughout the months of March and early May.  A test pile delivery will occur Wednesday, Feb. 6 consisting of three truckloads.

These trucks will be entering and leaving Marine Corps Base (MCB) Hawaii through the Mokapu Road gate as they are restricted from entry through the H-3 gate due to their oversized dimensions.  All deliveries will be assisted by Honolulu Police Department escorts on all city and state roads to the Mokapu Road gate.

Below is a list of the tentative production pile delivery dates.  Deliveries will occur mid-day.  Please note that these dates and times are subject to change.

March 15 and 18 - 20 truckloads total (approximately 8-10 truckloads per day)

March 25 - 1 truckload

May 3 and 6 - 15 truckloads total (approximately 8-10 truckloads per day)

Updates and changes will be available online at http://www.mcbhawaii.marines.mil/News/AlohaNewsletter.aspx.  The MCB Hawaii noise hotline is 257-8832.


Johanna Marizan-Ho

Marine Corps Base Hawaii

Phone:257-8832